Regional Autonomous Corporation of La Guajira

Environmental sustainability, Everyone's Commitment


Main Menu

PERIODIC CORPOGUAJIRA CONTIGO NEWS

ACTS BEFORE THE CORONAVIRUS

PUBLIC HEARING TO FOLLOW UP ON THE ACTION PLAN – VALIDITY 2021

PARTICIPATION PLAN CORRUPTION 2022

Participatory budget

PGAR FORUM 2020 – 2031

PGAR 2020 2031

CNSC

EARLY WARNING FOR DEFORESTATION

Early Detections of Changes in Key Ecosystems of the Caribbean and the Colombian Orinoquia

MIMAC TRAINING

CONSULTATION FOR FIXING TARGETS

GEODATABASE -GDB

RCD

AT THEM – USED ​​COOKING OIL

Territorial Planning Information

Information Risk Management

SAT

SATISFACTION SURVEY

ECOGUAJIRA

ACTION PLAN 2020 – 2023

Vital

VITAL

PQRSD ENVIRONMENTAL AND COMPLAINTS

PQRSD1

Road Wayurey

Facebook

Videos

Transparency and Access to Public Information

YOUTH EMPLOYMENT

Facebook

Calendar of Events and Publications

February 2026
The M X J In S D
 1
2345678
9101112131415
16171819202122
232425262728  

Facebook

Facebook

Translate this site


by Transposh - Plugin de traducción para WordPress

Files

This is how the work is progressing to prevent the overflow and erosion of the Tapias River.

TAPIA WORKS 1

Excavation with machinery to prevent flooding in the Chavas sector – Anaime

Representantes de Corpoguajira, They attended the invitation issued by the Honorable Council of Riohacha, with the purpose of providing a report on the progress status of the contract 038 of 2011, celebrated between Corpoguajira and the company La Macuira Inversiones y Construcciones S.A, for the construction of channeling works, channeling and longitudinal and breakwater protection works on the right and left banks of the Tapias River, to guarantee the continuity of the flow and avoid erosion and specific flooding of the Chavas sectors – Anaime; The Mangos II – Anaime; Two Pipes – Choles; The Stick – Matitas; Caracolí – Matitas; to the market – Matitas; Cadillal II – Choles; Canal Robles, Old Creek, Guaracaca and Guaracaquita; area surrounding the Pelechua township (Riohacha).

during the meeting, officials of this Corporation had the opportunity to explain the delay in the physical work of the contract, which has been due among other reasons to the increase presented several weeks ago, in the flows and levels of the river and the waiting time in the supply and disposition of the meshes.

At this time there are two work fronts in the towns of Anaime and Choles carrying out excavation and channeling work given that the levels of the Tapias River have dropped and allow machinery access..

TAPIA WORKS 2

Excavation with machinery for the collection of material in the El Palo sector – Matitas.

Despite the above Corpoguajira, On repeated occasions, it has continuously requested the contractor company through the audit and directly to speed up the execution of the works with which it contributes to the goal of the entity's Action Plan in a 32.6 %, and will result in an improvement in the quality of life of users in the sector..

It is important to clarify that the agreed deadline for the completion of the works is stipulated for the day 30 April 2012, date established in the minutes of initiation of the aforementioned contract, reason why Macuira Inversiones y Construcciones S.A, committed to increasing the workforce and availability of machinery to streamline the work.