Regional Autonomous Corporation of La Guajira

Environmental sustainability, Everyone's Commitment


Main Menu

PERIODIC CORPOGUAJIRA CONTIGO NEWS

ACTS BEFORE THE CORONAVIRUS

PUBLIC HEARING TO FOLLOW UP ON THE ACTION PLAN – VALIDITY 2021

PARTICIPATION PLAN CORRUPTION 2022

Participatory budget

PGAR FORUM 2020 – 2031

PGAR 2020 2031

CNSC

EARLY WARNING FOR DEFORESTATION

Early Detections of Changes in Key Ecosystems of the Caribbean and the Colombian Orinoquia

MIMAC TRAINING

CONSULTATION FOR FIXING TARGETS

GEODATABASE -GDB

RCD

AT THEM – USED ​​COOKING OIL

Territorial Planning Information

Information Risk Management

SAT

SATISFACTION SURVEY

ECOGUAJIRA

ACTION PLAN 2020 – 2023

Vital

VITAL

PQRSD ENVIRONMENTAL AND COMPLAINTS

PQRSD1

Road Wayurey

Facebook

Videos

Transparency and Access to Public Information

YOUTH EMPLOYMENT

Facebook

Calendar of Events and Publications

December 2023
The M X J In S D
 123
45678910
11121314151617
18192021222324
25262728293031

Facebook

Facebook

Translate this site


by Transposh - Plugin de traducción para WordPress

Files

District application for the environmental permit for the construction of the bridge over the mouth of the Ranchería River, has technical inconsistencies: Corpoguajira

The environmental authority explains that the process is within the legal terms. The permit would be issued once the required adjustments are made by the environmental entity.

Given the public order situation presented yesterday due to the poor condition of the structure of the bridge located over the mouth of the Ranchería River (Riohacha), The Regional Autonomous Corporation of La Guajira reported that the procedures for the riverbed occupation and forest exploitation permit, are executed within the legal terms established by Decree 1076 of 2015, which stipulates a period of 90 business days.

Additional to the before, the environmental authority argued that in the request submitted by the District of Riohacha, el 12 April 2022, various technical inconsistencies, which is why Corpoguajira convened a work table last 19 de mayo, In order to remedy this situation, in which representatives of the territorial entity participated, the Department for
Social Prosperity, the contractor company and the supervision of the work.

As explained by Corpoguajira, el 24 May 2022 field visit was carried out. Subsequently, a new revision of the partial information presented was carried out., which again included some differences in the document; situation that was communicated to the District in order to solve this impasse.

It should be noted that the situation of public calamity due to the damage to the bridge over the Riito, was declared by the Mayor's Office of Riohacha, by decree No. 053 the 29 June of the 2022.
Bearing in mind that the Ranchería River has a planning instrument, it became necessary to evaluate the risk factor represented by the area to be intervened, Therefore, the Planning Advisory Office of Corpoguajira carried out a study regarding the uses of the sector involved., issuing its concept of environmental management in the area of ​​influence of the project, el 5 July 2022.

In order to unify criteria in riverbed occupation and forest exploitation permits, regarding the project in question, today (12 of July), a new table will be developed
work between Corpoguajira and the District of Riohacha to definitively solve the technical inconsistencies that said request still presents. In this sense, Corpoguajira reported that the permit would be issued once the adjustments are made by the District Mayor's Office.

Finally, Corpoguajira pointed out the importance of continuing to comply with the guidelines established in current environmental regulations in order to preserve, protect and conserve natural resources and the environment of its jurisdiction.